Fictional starting position
A fictional panel order has an accepted assembly and artwork. Before manufacture, a supplier proposes another board and finish because the original stock is unavailable.
Examine the record
The accepted record names the original exact variant and supported use. The proposed substitutes differ in construction and finishing. Approval of artwork does not authorise every material or performance change.
Decision steps
Create a proposed assembly version and record the changed components, reason and affected requirements.
Request applicable product, finishing, compatibility and receiver evidence. Route performance and commercial questions to their responsible reviewers.
Obtain a fresh scoped approval before release. Preserve the original accepted version and record the version actually supplied.
Bounded outcome
The fictional project can accept, reject or further review the substitute with an attributable decision. A copied approval or a similar family name does not silently authorise production.
Apply the lesson
Transfer the lesson from “A material substitution requires a fresh approval” into a fresh real project record. Start with: What exactly changed? Which approval questions are reopened? The scenario above is fictional; the answers, evidence versions and actual changes on your project must be recorded independently.
- What exactly changed?
- Which approval questions are reopened?
- Which version was actually delivered?
Method
- Create a proposed assembly version and record the changed components, reason and affected requirements.
- Request applicable product, finishing, compatibility and receiver evidence. Route performance and commercial questions to their responsible reviewers.
- Obtain a fresh scoped approval before release. Preserve the original accepted version and record the version actually supplied.